Rebuilding Office IT Infrastructure After A Fire

Office infrastructure · Anonymous customer project

After a fire damaged all equipment in an office data centre, T Strategy helped rebuild the infrastructure the business depended on—from consultation and design to implementation and ongoing support.

Completed server rack installation
Completed server rack installation.
Network cable routing
Network cable routing
Rear rack connections
Rear rack connections
Patch panels and switching
Patch panels and switching
Connected network equipment
Connected network equipment

The challenge

Rebuild The Office IT Foundation.

The fire damaged all equipment in the office data centre. The project covered the entire office infrastructure, bringing the physical installation, computing, connectivity, power protection and backup arrangements into one scope.

Our role

One Team, From Planning To Post-Implementation Support.

01

Consult And Design

Provide consultation and design for rebuilding the office infrastructure.

02

Implement The Infrastructure

Install and integrate the equipment and connections across the office environment.

03

Support After Completion

Provide post-implementation support for the completed infrastructure.

What The Project Covered

  • Network cabling and equipment racks
  • Servers and storage
  • Network switches and wireless access points
  • Firewall and UPS
  • Data backup

The outcome

A Working Infrastructure, With Continuing Support.

T Strategy reports that the completed infrastructure has continued to work well, with no customer complaints reported since completion.

Your next step

Planning An Office Infrastructure Rebuild?

Talk to us about your servers, network, backup and support needs.

Discuss your infrastructure

EXPERIENCE THROUGH THE YEARS

Customer Feedback & Project Experience

CUSTOMER FEEDBACK · 2016

Migration, Backup & Storage

Ms. Pam expressed satisfaction with the technical services, project support and deliverables for a migration, backup and storage project.

Ms. Pam

Summary of customer feedback received in 2016 · Project in 2015

PROJECT EXPERIENCE · 2015

Technology For Office & Production

Deployment of desktop computers, laptops, tablets and printers for office and production operations, with after-sales support.

Mr. Hadi

Summary of a historical project record · Go-live September 2015